Real projects, real results. From large-scale industrial decommissioning to emergency call-outs, every project is delivered with precision, safety, and accountability.

AkzoNobel Industrial Decommissioning
Industrial Decommissioning

AkzoNobel Industrial Decommissioning

North East England 8 weeks

Demolition of two structures on a live, operational top-tier COMAH plant. Structural steel removal and full site clearance, delivered alongside ongoing operations.

View details
Emergency Fire Damage Response
Emergency Response

Emergency Fire Damage - Council Partnership

North East England 2 weeks

Emergency mobilisation to a fire-damaged commercial building within 3 hours. Working directly with the local council to make the structure safe.

View details
Middlesbrough Old Town Hall
Demolition & Temporary Works

Middlesbrough Old Town Hall

Middlesbrough 4 weeks

Asbestos removal, demolition and engineered temporary works to a landmark heritage building. The structure was taken down while the main clock tower was retained on new supporting legs.

View details
AkzoNobel Decommissioning
Industrial Decommissioning

AkzoNobel Industrial Decommissioning

North East England 8 weeks

Demolition of two structures on a live, operational top-tier AkzoNobel COMAH plant. Delivered alongside ongoing site operations under strict permit-to-work, safety and environmental controls, the works included structural steel removal and complete site clearance, completed over an eight-week programme.

Key Challenges

  • Active adjacent operations requiring careful phasing
  • Live, operational top-tier COMAH site requiring strict permit-to-work controls
  • Complex structural steel removal

Delivered on time, 95%+ waste diverted from landfill, zero incidents.

Emergency Fire Damage Response
Emergency Response

Emergency Fire Damage - Council Partnership

North East England 2 weeks

Emergency mobilisation to a fire-damaged commercial building within 3 hours of the call. Working directly with the local council to make the structure safe, demolish unstable sections, and secure the site for public safety.

Key Challenges

  • Structural instability requiring immediate assessment
  • Public safety cordon management
  • Working under emergency conditions with council oversight

On-site within 3 hours, structure made safe within 48 hours, site fully cleared and secured.

Middlesbrough Old Town Hall
Demolition & Temporary Works

Middlesbrough Old Town Hall

Middlesbrough 4 weeks

A landmark heritage project at Middlesbrough Old Town Hall. WSS carried out asbestos removal and full structural demolition while preserving the listed clock tower. Engineered temporary works and new supporting legs were installed so the tower remained standing as the surrounding building was safely brought down.

Key Challenges

  • Retaining and protecting the listed clock tower throughout demolition
  • Designing and installing temporary works and new supporting legs for the tower
  • Asbestos removal prior to structural demolition

The building was safely demolished while the landmark clock tower was retained intact on its new supporting legs.